Guide to application for water
consumption:
|
A. On the installation of indoor and outdoor
pipes, customers must present the design blueprint (two sets) to the
Company's Business office for approval, to which the project can be
carried out.
1. Documents for temporary water consumption: unit letter of introduction,
project approval, plane location drawing (1:500).
2. Documents for formal water consumption: unit letter of introduction,
project approval, plane drawing of factory area water supply (1:500),
general pipe net plane drawing (1:500), vertical section drawing and
indoor water supply system drawing.
B. Procedure:
1. Customer is to fill out a "Design Entrustment" at the Business
office. (1 day) 2. Transfer the "Design Entrustment" to Water-saving
office for water consumption quota (1 day). The Water-saving office
and the designer make the inspection and decide the quota (1-3 days).
3. The business office and Water-saving office present the inspection
and quota result to the executive manager for approval and then transfer
it to the designers (1-2 days).
4. The designers start the project design and the project budget
for the project construction company (2-4 days).
5. The project construction company notifies the customer to pay
the construction cost and arrange the construction (1-3 days), 6-14
days in all. The construction duration will be stated in the construction
contract.
6. When the construction is completed, no water supply can be unbolted
until the construction is checked and approved (3-4 days).
C. Application for unbolted water entails unit letter of introduction
and entrustment agreement for water payment, to be followed by the
procedure of water examination, unbolting and examination fee payment
(2-3 days). |
|